DN Research · AI infrastructure and power · 2027 edition
A nuclear power agreement can secure a commercial relationship years before it supplies a new data centre. To understand what an AI energy deal delivers, separate existing generation, additional capacity, regulatory permission, grid delivery and the date the customer needs electricity.
Research cutoff: 25 November 2026. The cases below are selected US arrangements, not a global project ranking. Future operating dates are attributed targets, not observed deliveries.
What Matters
- A purchase from an operating plant, a restart, a capacity uprate and a new reactor have different dependencies.
- Contracted megawatts do not automatically equal new generating capacity. Energy attributes, financial hedges and physical delivery must be identified separately.
- A construction permit, environmental finding and operating authority establish different milestones.
- The gap between data-centre demand and expected nuclear availability has a measurable energy requirement, even when contract prices remain private.
The Signal
The public record contains several different kinds of progress under the same broad label of “AI nuclear deal.” Constellation’s June 2025 announcement with Meta concerned a 20-year arrangement supporting Clinton’s continued operation from June 2027. Google and Kairos announced a new-build path through TVA targeting Hermes 2 operation in 2030. Amazon’s October 2026 Indiana announcement describes an agreement to explore a 960 MW project. These are different economic propositions, not interchangeable units in a capacity scoreboard. Clinton announcement; Google–Kairos–TVA announcement; Amazon Indiana announcement.
The useful comparison therefore starts with a question: what observable event must happen before this agreement can serve the stated demand? Answering it requires a sequence of dated records, not simply a larger total of announced gigawatts.
DN Alpha Thesis
The valuable asset is a project-to-demand record. It connects the customer, contract type, underlying plant, regulatory scope, delivery route and timing gap. That record can support procurement decisions, investment research and machine retrieval without presenting a commercial ambition as electricity already available.
Five records to read before adding the megawatts
| Arrangement | What the reviewed record says | What must remain separate |
|---|---|---|
| Meta / Clinton | Twenty-year agreement starting June 2027; announced output relationship of 1,121 MW | Existing generation preserved versus the separately announced 30 MW uprate |
| Microsoft / Crane | Restart project; Constellation targets service in 2027 and describes 835 MW restored | Restored generation versus operating authority and completed restart |
| Google / Kairos / TVA | Hermes 2 commercial plan: up to 50 MWe; announced operations target of 2030 | Commercial configuration, historical permit scope and eventual operating permission |
| Google / Constellation | November 2026 disclosure describes about 890 MW of incremental uprates, first expected in 2028 | Incremental generation versus a separate 2,700 MW financial load-following agreement |
| Amazon / X-energy / AEP, Indiana | October 2026 agreement to explore 12 reactors targeting 960 MW | Exploration agreement versus a financed, authorised and completed generating project |
Sources: Constellation, 3 June 2025; Crane project page, reviewed 25 November 2026; Kairos, August 2025; Constellation, 9 November 2026; Amazon, 19 October 2026.
Existing power, restarted power and new power solve different problems
Keeping an operating asset available can be economically significant. It can support maintenance, investment and the continued supply that a counterfactual closure would remove. But preserved output is different from additional output. A total that combines both needs to show the categories and the counterfactual, rather than presenting every contracted megawatt as a newly constructed plant.
Clinton illustrates that distinction. The announced Meta arrangement supports the plant’s continued operation and includes a separately described 30 MW uprate. The NRC subsequently announced renewed operating authority for Clinton to April 2047 on 16 December 2025. The evidence therefore contains a commercial commitment and an identifiable regulatory event, each with its own date and meaning. Contract announcement; NRC licence-renewal announcement.
A restart has a different chain of work. The operator must restore the facility and satisfy the requirements for returning to power operations. The prior existence of the plant can provide valuable infrastructure, but it does not turn a new commercial agreement into an automatic right to resume generation.
For Crane, the September 2026 Federal Register notice records a final environmental assessment and finding of no significant impact associated with proposed reauthorisation. That is a meaningful completed milestone. It is not, by itself, a report that the plant has restarted. Constellation’s project page continues to present 2027 as its expected service year. NRC notice, 25 September 2026; Operator’s project description.
A permit must match the project being described
The NRC explains distinct US licensing routes. The Part 50 approach separates construction permission and an operating licence; a Part 52 combined licence includes conditions that must be met for operation. A record should therefore name the authorisation and its scope, rather than compress every event into a single “approved” status. NRC licensing backgrounder.
Hermes 2 shows why version control matters. The NRC project page records construction permits issued on 21 November 2024 for an initial two-reactor configuration, each rated at 35 MW thermal. Kairos’s August 2025 commercial announcement describes a revised single-reactor configuration delivering up to 50 MW electric. The company’s April 2026 release records groundbreaking for that commercial demonstration project. Those records should be preserved as different scopes and dates. NRC construction-permit record; Kairos commercial configuration; Kairos groundbreaking, 17 April 2026.
This review has not established the status of every regulatory change required for the announced commercial configuration. The earlier permit should not be presented as proof that every subsequent design change is authorised. Equally, a difference between a project summary and a later announcement is not evidence that the project is acting unlawfully. It is a reason to retain the unresolved field and inspect the relevant docket.
Thermal and electrical ratings also cannot be substituted. A reactor’s thermal output measures heat; the electrical output is the power supplied after conversion. The commercial unit, regulator docket and power basis belong in the same record.
The customer may be buying several different products
A commercial relationship can combine energy, capacity, environmental attributes and financial exposure. The question is not merely whether it carries the label PPA. Ask which party generates, which party takes physical delivery, which intermediary serves the load, what attributes transfer and how payments change when output or demand differs from expectations.
Google’s Hermes 2 announcement describes TVA purchasing electricity from Kairos and Google receiving clean-energy attributes through TVA. That is a three-party structure. It should not be rewritten as a private wire carrying the reactor’s entire output directly into one Google building. Google’s description of the arrangement.
Constellation’s November 2026 disclosure provides another distinction: the 890 MW uprate programme sits alongside a separate 2,700 MW financial energy load-following agreement with Google. Adding those figures and calling the result newly built nuclear capacity would mix a generation increment with a different commercial product. Constellation third-quarter 2026 results.
The full contracts were not reviewed here. Consequently, this article does not assign undisclosed prices, completion guarantees, curtailment priorities or damages. A public announcement can establish an announced structure; it cannot establish clauses that have not been disclosed.
Measure the gap between demand and expected supply
A data centre may need power before the associated project is expected to deliver. That gap exists even if everyone eventually meets their contractual obligations. The operator needs an interim source, a delayed deployment, a flexible workload plan or a combination.
Consider a synthetic example: 100 MW of load at a 90% average load factor, starting on 1 January 2027. The scenario assumes the intended supply becomes available on 1 January 2028. The one-year gap requires:
100 MW × 24 hours × 365 days × 90% = 788,400 MWh.
At an illustrative bridge-energy price of $80 per MWh, the energy-only cost is $63.072 million. These are scenario inputs, not a quoted tariff, a disclosed project delay or an estimate of any named company’s bill. The calculation excludes transmission charges, demand charges, taxes, backup facilities, network losses, financing and carbon attributes.
The number helps frame negotiations. Which party pays for interim energy? Does the commercial start date depend on plant completion, grid connection or another condition? Can the customer reduce committed demand? What happens if a data centre is late while the supply is ready? A delayed reactor and a delayed customer create different exposure.
Use the power-delivery gap calculator
Enter the date demand begins, an assumed supply-ready date, average load and a bridge-energy price. The result is a planning scenario. It does not estimate the probability that a nuclear project will finish, and it does not assign a live market price.
DN Energy Delivery Gap Calculator
Change the assumptions to calculate an illustrative scenario. Calculations run in your browser. Choosing Export downloads your inputs and results as a JSON file. This page also uses the site’s standard analytics. Scenario exports are separate from the article’s source evidence.
The dates drive exact UTC calendar-day differences, including leap days. The separate annual-energy comparison uses a standard 8,760-hour planning year. Its capacity factor is a user assumption, not a forecast derived from a reactor’s historical or future performance.
A result of 100% annual energy coverage does not establish that supply meets demand in every hour. Equal annual totals can coexist with outages, delivery constraints and mismatched load profiles. A credible hourly matching claim needs interval data, contract eligibility, location and treatment of interruptions. The EIA’s definitions distinguish power capacity, energy produced and capacity factor; the calculator preserves that separation. EIA capacity and generation explainer; EIA capacity-factor definition.
Who carries the waiting cost?
The waiting cost can sit with a project sponsor, a utility, a customer, a lender or other ratepayers, depending on documented terms. The right analytical move is to trace the obligation. An organisation announcing participation is not necessarily guaranteeing construction, and an investment in a developer is not necessarily a purchase of a finished plant.
A practical contract review should distinguish development funding, equipment commitments, electricity payments, network-upgrade contributions and termination liabilities. These cash flows occur at different stages and may have different conditions. If a term is undisclosed, mark it as undisclosed instead of assuming a standard allocation.
For a buyer, the central question is service continuity: what supplies the workload when the nominated generator is unavailable? For a developer, it is bankable demand and delivery obligations. For a community, it is which costs and benefits are contractually assigned, what public decisions remain, and how any claims will be measured after operation begins.
The calculator only values an energy bridge. It does not settle these allocation questions. Its result becomes useful when attached to a contract clause, budget owner and assumption date.
A project record humans and agents can reuse
The machine-readable record should be narrow enough to prevent a retrieved fact from changing meaning. Store the project name and stable identifier separately from the customer, commercial agreement and generating units. A multi-plant framework is not the same entity as its first reactor.
| Field | Required distinction | Example of an error prevented |
|---|---|---|
| Capacity type and unit | Existing, restored, uprate or planned new; MWe versus MWth | Counting preserved output as all-new capacity |
| Milestone and status | Announced, applied, authorised, under construction, commissioned or observed generation | Rendering a target as a completed event |
| Date type | Announcement, evidence retrieval, target, contractual commencement or observed operation | Using the signing date as the electricity start date |
| Counterparty and product | Generator, utility, customer; energy, capacity, attributes or financial agreement | Adding unlike contractual quantities together |
| Source and boundary | Issuer statement, regulator record, full contract or measured output | Turning an operator claim into independent verification |
Keep previous versions. When a date changes, retain the earlier target and the newer evidence rather than silently overwriting the row. The resulting record can show actual progress, revised plans and unresolved dependencies without inventing a probability score.
How to assess the next announcement
- Identify the physical asset. Locate the specific plant or programme, not just the technology company announcing the deal.
- Classify the increment. Is it preserved output, restored output, an uprate, a new reactor or an option to explore development?
- Read the current regulatory event. Match its docket, configuration, unit and date to the commercial claim.
- Trace delivery and attributes. Identify the generator, grid, serving utility, customer and product purchased.
- Price a timing scenario. Use explicit demand dates, load factors and bridge prices. Keep cost allocation separate.
- Record the next observable milestone. Define which document or output would advance the status and which assumption would need changing.
This sequence also improves an AI assistant’s answer. Instead of saying a company has “secured nuclear power,” it can say whether the evidence concerns an existing plant, a future commercial start, a completed permit milestone or a proposed development. That additional precision is directly useful to a procurement team, researcher or reader assessing an infrastructure narrative.
Methodology and limits
DN selected five US arrangements to illustrate distinct commercial and physical categories. We reviewed issuer announcements, relevant regulator material and official energy definitions available by 25 November 2026. We did not inspect complete private contracts, independently estimate engineering completion probabilities or measure delivered electricity for these arrangements.
Regulator project pages can lag newer orders and announcements. Where the reviewed records differ in scope, the evidence record preserves the difference. The Crane environmental milestone is tied to the dated Federal Register notice; the Hermes 2 configuration issue remains explicitly unresolved in this review.
The calculator assumes constant average demand, a single supply-ready date and a flat energy-only bridge price. It does not model staged commissioning, hour-by-hour dispatch, losses, contract penalties, fuel availability or outage distributions. Tests cover a full-year gap, a leap year, zero and reversed date gaps, annual energy above demand, and invalid dates or percentages. Scenario outputs are reproducible arithmetic, not measured commercial results.
Frequently asked questions
Does signing a nuclear PPA mean new electricity is available immediately?
No. The agreement may concern existing production, future operation, a restart or capacity still to be developed. Establish the asset, start conditions and delivery route before interpreting availability.
Is a construction permit the same as permission to operate?
Not under the two-stage Part 50 process. Other licensing routes have their own conditions. Record the specific authorisation instead of using a single approved/not-approved label.
Can all announced megawatts be added together?
Only when the quantities share a defined basis and have been checked for overlap. Existing output, uprates, multi-project ambitions and financial load-following arrangements cannot automatically form one new-capacity total.
Does 100% annual energy coverage mean 24/7 matching?
No. Annual totals do not show the timing of generation and demand. Hourly matching needs interval evidence and clear treatment of outages, geography and eligible attributes.
Does the calculator predict a project’s completion date?
No. The supply-ready date is an input. The tool calculates an energy gap and an illustrative energy-only cost from the assumptions the user provides.
Why include older announcements in a 2027 edition?
The agreement’s original date remains part of its evidence trail. A current review should add subsequent milestones and preserve the earlier record, rather than redate the announcement or imply that future operation has occurred.
Primary sources
- Constellation: Meta and Clinton agreement, 3 June 2025.
- NRC: Clinton and Dresden licence renewals, 16 December 2025.
- Constellation: Crane project information.
- NRC: Crane environmental notice, 25 September 2026.
- Google: Kairos and TVA structure, 18 August 2025.
- Kairos: Hermes 2 commercial configuration.
- NRC: Hermes 2 construction-permit record.
- Kairos: groundbreaking, 17 April 2026.
- Constellation: third-quarter results, 9 November 2026.
- Amazon: Indiana exploration agreement, 19 October 2026.
- NRC: licensing-process explanation.
- EIA: generating capacity and generation; capacity factor.
Continue the infrastructure record
Read DN’s analysis of AI and Bitcoin competing for electricity and the boundaries behind data-centre water claims. Together, these questions connect power procurement with the physical constraints surrounding usable compute.
Build a useful record with DN
Have a product, platform or dataset that can make this decision clearer? Propose a documented product walkthrough, a clearly labelled sponsored feature or a scoped data collaboration. Bring the evidence, access and limitations that readers need to assess it.
Discuss coverage or a research partnership. Commercial participation does not buy a favourable finding.
Original cover: AI-generated editorial illustration; not a photograph of a real project. Download the dated evidence record (JSON). The 2027 label identifies the planning edition; sources were reviewed on 25 November 2026.